Planning & Scheduling
|
Construction Scheduling
for a Resort Hotel
|
ACM was contracted to
functionally review and modify the overall construction
schedule for completion of a large resort hotel. ACM
performed an extensive review of the plan,
specifications, and the existing schedule. From
information that was gathered in the review, from site
walk downs, and in meetings with the project managers,
superintendents, and subcontractors, ACM personnel
gathered progress and proposed extensive revisions to the
project schedule. For the remainder of the project, ACM
conducted bi-weekly status updates of the schedule
identifying variances and suggested work-around solutions
leading to a successful completion.
|
Planning & Scheduling
Support for Low Pressure Turbine Components Replacement
Project
|
ACM provided planning support
for the Low-Pressure Turbine Enhancement project team at
a major utility. The main project entailed the
replacement of three low-pressure turbine rotors and
diaphragms. The project team was also responsible for
capital projects which included: 1) Replacement of the
moisture removal section of two moisture separator
reheaters; 2) modifications to the gland steam sealing
system; 3) replacement of the differential expansion
instrumentation; 4) modifications to the reverse power
relay system; 5) modification to the generator hydrogen
coolers; and 6) modifications to the main lube oil and
jacking oil systems. The preventive and corrective
maintenance normally associated with a refueling outage
was incorporated into the turbine group's schedule.
Schedule support included the
development of a detailed schedule for all work within
the turbine group scope. The development of the schedule
involved coordination between the owner utility,
equipment supplier, and turbine replacement manager, and
the site labor broker. The scheduling support also
included interfacing with the plant outage management
group.
|
Managing
Work Order Backlog and Maintenance Resources
|
ACM developed and implemented a
maintenance scheduling system for a
pharmaceutical-manufacturing complex. The customer's
objective was to increase the number of scheduled work
orders, reduce the work order backlog, and reduce
emergency work orders.
ACM worked with maintenance
management and supervision to establish work order
priorities. The development of priorities included
preventative maintenance, good management practices, and
corrective maintenance. ACM staff integrated the
customer's mainframe computer based maintenance system
with a PC based project management system to provide
scheduled maintenance crews with prioritized work orders.
ACM personnel led weekly meetings to review work
assignments and previous week's progress.
Training was provided to the
maintenance organization on project management concepts
and how to run the PC based system and use its reports.
Training was also provided to plant operations and plant
engineering to inform them of maintenance's objectives to
improve performance.
The implementation of the
scheduling system facilitated the increased confidence of
operations in the maintenance effort by reducing the time
that work orders were backlogged, establishing priorities
for non-emergency work, and the reduction of emergency
work orders.
|
Scheduling
Services for a Nuclear Power Plant
|
ACM was contracted by an
investor owned utility to perform schedule development
services on a nuclear power plant. ACM personnel
developed detailed schedules for modification projects
performed during the various outages. This included
developing detailed logic, utilizing the owner's
scheduling system, integrating modification schedules
into the overall plant outage schedule, and interfacing
with contractors. The number of projects varied between
30 and 50 depending upon the outage.
During non-outage periods,
efforts were concentrated on development of scope
packages consisting of an item plan, summary schedule,
and conceptual estimate. The packages were provided to
plant operations for budget approval. Based on budget
approvals and completion of design and procurement, the
item packages were statused as available for work in case
of a forced outage or included in the overall planned
outage.
During an outage, the
responsibilities shifted to continuous monitoring and
updating of each schedule to reflect current status and
progress. In addition to schedule responsibilities, cost
and performance measurement reporting were established.
The cost and schedule data were combined into a weekly
outage report.
Automotive
Construction
Maintenance Management
Training
Utilities
Project Management
Planning & Scheduling
Cost Estimating
Dispute Resolution
|