Utilities Projects
|
Scheduling Services for
a Nuclear Power Plant
|
ACM was contracted by an
investor owned utility to perform schedule development
services on a nuclear power plant. ACM personnel
developed detailed schedules for modification projects
performed during the various outages. This included
developing detailed logic, utilizing the owner's
scheduling system, integrating modification schedules
into the overall plant outage schedule, and interfacing
with contractors. The number of projects varied between
30 and 50 depending upon the outage.
During non-outage periods,
efforts were concentrated on development of scope
packages consisting of an item plan, summary schedule,
and conceptual estimate. The packages were provided to
plant operations for budget approval. Based on budget
approvals and completion of design and procurement, the
item packages were statused as available for work in case
of a forced outage or included in the overall planned
outage.
During an outage, the
responsibilities shifted to continuous monitoring and
updating of each schedule to reflect current status and
progress. In addition to schedule responsibilities, cost
and performance measurement reporting were established.
The cost and schedule data were combined into a weekly
outage report.
|
Planning
& Scheduling Support for Low Pressure Turbine
Components Replacement Project
|
ACM provided planning support
for the Low-Pressure Turbine Enhancement project team at
a major utility. The main project entailed the
replacement of three low-pressure turbine rotors and
diaphragms. The project team was also responsible for
capital projects which included: 1) Replacement of the
moisture removal section of two moisture separator
reheaters; 2) modifications to the gland steam sealing
system; 3) replacement of the differential expansion
instrumentation; 4) modifications to the reverse power
relay system; 5) modification to the generator hydrogen
coolers; and 6) modifications to the main lube oil and
jacking oil systems. The preventive and corrective
maintenance normally associated with a refueling outage
was incorporated into the turbine group's schedule.
Schedule support included the
development of a detailed schedule for all work within
the turbine group scope. The development of the schedule
involved coordination between the owner utility,
equipment supplier, and turbine replacement manager, and
the site labor broker. The scheduling support also
included interfacing with the plant outage management
group.
|
Waste
Wood Procurement - Generation Project
|
ACM provided procurement
services for waste wood products, a utility holding
company of an investor owned utility. The client was
involved with several co-generation facilities and ACM
drafted contracts for suppliers, researched and
investigated potential suppliers, negotiated contracts,
and assisted in implementation of supply sources for the
projects. ACM also developed schedules, budgets, and
evaluated return on investment for the waste wood
processing facilities.